During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?
During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?
To address the concern that the project did not deliver the expected business value, the project manager should review the business benefits realization plan with the stakeholders. This plan identifies the activities necessary to achieve the planned benefits, ensuring that the project's outcomes align with the expected business value. It provides a timeline and the tools and resources necessary to fully realize the benefits over time.
B is correct. Projects may perfectly follow schedule, fulfill requirement and meet quality but still can't achieve desired benefit.
I think it is B, answer is found on p.187 of PMBOK 7th ed.
there is no business benefits realization plan in pmbok!
neither the business value specified in project management plan
pmbok 7th ed. pg.187.
"BENEFITS REALIZATION PLAN: A document outlining the activities necessary for achieving the planned benefits. It identifies a timeline and the tools and resources necessary to ensure the benefits are fully realized over time...."
I chose B because the question was talking about business value. Another word for "benefits" that can come out of the project.
A. Review the project management plan tasks with the stakeholders.
B is correct.
B is correct
B. Review the plan with the Stakeholders.
Reviewing the business benefit plan can help to determine if the project objectives has been met
B. Review the business benefits realization plan with the stakeholders
Voted B
B is correct
B IS CORRECT
A OR D
C. Review the project management plan budget with the stakeholders.