Question 1012

A project manager learns that the performance of a high-performing project team member is deteriorating. This team member is a key member of the project.

Which action should the project manager take to motivate and enhance the project team member's performance?

    Correct Answer: D

    When faced with a high-performing team member whose performance is deteriorating, it is crucial for the project manager to understand the root causes of this change. Discussing the issue directly with the team member allows the project manager to gather insight into any personal or professional challenges the team member might be facing. By working together on an agreed solution, the project manager can help address these challenges, provide necessary support, and formulate a plan to enhance the team member's motivation and performance. This approach fosters open communication and demonstrates the project manager's commitment to the well-being and success of their team.

Discussion
517f9daOption: D

D. Discuss the issue with the team member and work on an agreed option Discussing the issue directly with the team member allows the project manager to understand the underlying reasons for the performance decline and collaborate on a mutually agreeable solution, addressing any personal or professional concerns.