Correct Answer: AThe project manager should plan to address the issues through backlog grooming and incorporate them into the next sprint. This is a standard procedure in Agile methodology, where feedback from the product owner during demonstrations or sprint reviews is used to refine the backlog and ensure that the software being developed meets the needs and expectations of the stakeholders. Escalating issues to the steering committee or referring to the change management plan or business requirement document does not align with the iterative and collaborative nature of Agile projects, and delaying the issues until the second version of the software would ignore the immediate feedback and needs of the product owner.