PgMP Exam QuestionsBrowse all questions from this exam

PgMP Exam - Question 213


A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared.

During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?

Show Answer
Correct Answer: C

During stakeholder engagement planning, the program manager should consider the expectations of program benefits, the level of influence of each stakeholder, and the organizational culture. Understanding stakeholders' expectations helps in aligning the program's objectives with their needs and interests. Recognizing the level of influence of stakeholders is crucial for prioritizing engagement efforts and managing potential impacts on the program. Additionally, being aware of the organizational culture is important for devising effective communication and engagement strategies that resonate with stakeholders and align with the organization's values and norms.

Discussion

7 comments
Sign in to comment
hanyulinOption: C
Dec 20, 2023

C is the right answer

tsangckl
May 20, 2021

Answer is C ref. SPM 5.3

yinfei
Mar 27, 2022

yes its C, the tricky one is B is so similar to C

[Removed]
Dec 19, 2023

C. Expectations of program benefits, level of influence, and organizational culture. These aspects are crucial for effective stakeholder engagement: Expectations of Program Benefits: Understanding what different stakeholders expect to gain from the program helps tailor engagement strategies to address their interests and concerns, ensuring that their needs are aligned with the program's objectives. Level of Influence: Recognizing which stakeholders have significant influence over the program or within the organization aids in prioritizing engagement efforts and managing potential impacts on the program. Organizational Culture: Being aware of the organizational culture helps in shaping the communication and engagement approaches in a way that resonates with stakeholders and aligns with the organization's values and norms.

happykaurOption: C
Jan 14, 2024

During stakeholder engagement planning for a program, the program manager should consider the following aspects of stakeholders: C. Expectations of program benefits, level of influence, and organizational culture. Understanding stakeholders' expectations of program benefits is crucial for aligning the program's objectives with their needs and interests. The level of influence of each stakeholder can determine the impact they have on the program's success. Additionally, considering the organizational culture is important for effective communication and engagement strategies. This combination helps in devising a stakeholder engagement plan that is responsive to the needs and dynamics of all involved parties.

happykaurOption: C
Feb 25, 2024

Spm 5.3

tungdt
Jul 10, 2024

C is the best answer

tungdt
Jul 11, 2024

Sorry, I think again. I choose B. Expectations of program benefits for Business Case, program charter (high level). The question asks "stakeholders aspects" so organizational culture don't make sense and organizational culture for change.