CAPM Exam QuestionsBrowse all questions from this exam

CAPM Exam - Question 29


Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

Show Answer
Correct Answer: C

When a project manager seeks to bring some degree of satisfaction to all parties in order to temporarily or partially resolve a problem, the most appropriate technique is Compromise/Reconcile. This approach aims to find a middle ground where each party gives up something to reach a mutually acceptable solution, albeit a temporary or partial one. This technique ensures that all parties feel they have gained something, even if the resolution is not perfect or permanent, thereby reducing immediate tensions and allowing for progress.

Discussion

17 comments
Sign in to comment
ld212903Option: C
Dec 16, 2022

C Compromise/reconcile. Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict. This approach occasionally results in a lose-lose situation. Smooth/accommodate: Emphasizing areas of agreement rather than areas of difference

KanabiOption: C
Dec 27, 2022

exact wording: Compromise/reconcile. Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict. This approach occasionally results in a lose-lose situation.

[Removed]Option: C
Jul 4, 2023

As others have said below, there's really no mention of WHY it should be B. This answer is wrong. It should be compromise/reconcile. They bring some degree of satisfaction to all parties for a temporary or partial resolve of conflict.

Peri_Option: C
Dec 26, 2022

C pmbok 9.5.2.1

CalvinthePMOption: C
Mar 12, 2023

Smooth/accommodate. Emphasizing areas of agreement rather than areas of difference; conceding one’s position to the needs of others to maintain harmony and relationships. Compromise/reconcile. Searching for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict. This approach occasionally results in a lose-lose situation.

k_I_N_GOption: C
Apr 8, 2023

RIGHT ONE

Ibrahim_MOption: B
Apr 26, 2023

The technique that the project manager should use in this case is B. Smooth/Accommodate. This technique involves playing down differences while emphasizing common interests. The project manager should aim to create a temporary or partial solution to the conflict that satisfies all parties to some degree. This approach may be appropriate when the issue at hand is not critical and when there are time constraints.

RaaeOption: C
Jun 12, 2023

Compromise/Reconcile Both parties don't get a complete resolution and the solution is not permanent

Hicks_747Option: C
Apr 5, 2023

The Answer provided is wrong. The correct answer is C. Compromise/Smoothing. Check PMBOK 6th Edition, pg 349.

ChymKuBoyOption: C
May 23, 2023

C for sure

zbekcapmOption: C
Jun 13, 2023

Compromise

Cam77Option: C
Jun 14, 2023

Everyone agrees it's C.

SkelehoseaOption: B
Jun 23, 2023

B is the correct answer, smoothing provides a temporary solution.

Ajilox5Option: C
Jul 20, 2023

C should be correct

Akas2211Option: C
Nov 23, 2023

C 100%

Erry12Option: C
Jun 12, 2024

Pag 349, Compromise/reconcile technique explanation

Andrew_1980Option: B
Jul 6, 2024

B should be right as it is a temporary solution with partial satisfaction to all