Question 9

Five agile teams working together on a product recently performed release planning. Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished.

What should the project manager have done differently?

    Correct Answer: D

    The project manager should have ensured frequent and continuous integration of work to obtain early feedback and continuous learning. By doing so, integration issues would be identified and addressed early in the development process, preventing the accumulation of problems that are only discovered at the product level.

Discussion
KIKOption: A

scrum of scrum

aishOption: D

Voting for D Option A (Performing a Scrum of Scrums) is valuable for coordination and communication among the teams but may not directly address the root cause of the integration issues. The focus should be on preventing integration problems through continuous integration and early feedback rather than solely relying on problem-solving in Scrum of Scrums meetings.

HamiakzOption: A

The Scrum of Scrums is a time-boxed session in which a representative from each Team shares high-level updates on their respective team's work and articulates their progress and impediments.

SamPMP

I dont get how D was most rated one...

iuedemeOption: A

A- scrum of scrum Option D is contained in A

KennethTangOption: D

Continuous integration can spot the problems earlier

BuviDOption: D

D. Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

MamoonpkOption: D

Fail early than fail later

RachelZ

Why not B?

Uncle_Lucifer

The issue is integration, not the work or product of the individual team. That's why

Ravi4frenchOption: D

D. Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

Alphy07Option: D

The answer is D

Mahi_02021988Option: D

Answer is D

MbolatianaOption: D

D is the answer

ben7363728Option: D

D. Ensured frequent and continuous integration of work to obtain early feedback and continuous learning Most Voted

victory108Option: D

D. Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

BenPappoeOption: D

Voted D

Anna12675Option: D

d is correct