A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?
A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?
If the project needs to be completed two months earlier, the project manager should consider crashing the schedule. Crashing the schedule involves adding more resources or increasing work hours to shorten the project duration without changing the scope. This is a direct method to address the request for an earlier completion date while keeping the project's original objectives and deliverables intact.
A. Hold a stakeholder meeting to align timelines and scope expectations
vote A, need to get approval before make the change
A first then can based on the result to decide the next action. After A can be B or C