PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 513


A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.

What should the project manager do?

Show Answer
Correct Answer: B

If the project needs to be completed two months earlier, the project manager should consider crashing the schedule. Crashing the schedule involves adding more resources or increasing work hours to shorten the project duration without changing the scope. This is a direct method to address the request for an earlier completion date while keeping the project's original objectives and deliverables intact.

Discussion

3 comments
Sign in to comment
victory108Option: A
Oct 16, 2022

A. Hold a stakeholder meeting to align timelines and scope expectations

kevindebruyneOption: A
Aug 2, 2023

A first then can based on the result to decide the next action. After A can be B or C

DavidTriOption: A
Jul 10, 2024

vote A, need to get approval before make the change