Question 233

Which of the following are outputs of the Define Scope process in Project Scope Management?

    Correct Answer: C

    The outputs of the Define Scope process in Project Scope Management are the Project Scope Statement and Project Documents Updates. The Project Scope Statement defines the project's scope, including objectives, deliverables, constraints, and acceptance criteria. Project Documents Updates involve updates to various project documents that reflect any changes or clarifications related to the project's scope definition. This makes option C the correct answer.

Discussion
missyiOption: C

C is the correct answer.

ale1231Option: C

C. Project scope statement and project documents updates

UlrichIngOption: C

C. Project scope statement and project documents updates

MoonManBlueOption: C

C-Project Scope Statement and Project Documents updates-5.3

Andrew_1980Option: C

A - it's wrong as it's an output for Collect requirements process but not Define scope process

041ba31Option: C

C. Project scope statement and project documents updates The outputs of the Define Scope process in Project Scope Management are: Project Scope Statement: This document defines the project's scope, including its objectives, deliverables, constraints, assumptions, and acceptance criteria. It serves as a basis for making future project decisions. Project Documents Updates: The Define Scope process may result in updates to various project documents, such as the requirements documentation, assumptions log, constraints log, and other project-related documents. These updates reflect any changes or clarifications related to the project's scope definition.

PeteyPeteOption: A

The answer is A.

UlrichIngOption: A

A. Requirements documentation and requirements traceability matrix is also OUTPUT