Correct Answer: B, C, DTo address the situation where the project manager is concerned about meeting the deadline and complaints from stakeholders have been received about some team members' performance, the project manager should: 1) Perform a retrospective session, which allows the team to reflect on the work done so far, identify issues, and determine areas for improvement. 2) Implement daily team meetings to enhance communication and coordination among team members, leading to better project performance. 3) Request a manager performance review to gain insights from higher management or stakeholders which can help to highlight areas needing improvement or additional support. Introducing or redefining ground rules (option A) and conducting an annual review (option E) do not directly address the immediate performance concerns and meeting the deadline.