PMP Exam - Question 155


During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

Show Answer
Correct Answer: D

The Stakeholder Engagement Assessment Matrix is the correct document to review. This matrix helps identify gaps between the desired and actual engagement levels of stakeholders. It allows the project manager to evaluate how effectively stakeholders are being engaged and can highlight communication issues, such as a major stakeholder not being informed about recent developments.

Discussion

11 comments
Sign in to comment
emelbaOption: D
May 21, 2023

the stakeholder engagement assessment matrix helps identify gaps between desired and actual engagement levels of stakeholders.

Franco11
Oct 24, 2022

is it not consider an issue?

Ade1981
Dec 26, 2022

Now the PM is trying to find our the reason for this issue. So he needs to check the engagement document

victory108Option: D
Jun 4, 2023

D. Stakeholder engagement assessment matrix

MuntadherOption: D
Jul 24, 2023

After checking Stakeholder register. need to check stakeholder engagement assessment matrix

AsakthiOption: D
Aug 13, 2023

D. Stakeholder engagement assessment matrix

Lucky_CindyOption: D
Oct 16, 2023

D. Stakeholder engagement assessment matrix

huynq185Option: C
Oct 30, 2023

Check stakeholder register first

mesacgonOption: C
Nov 2, 2023

La respuesta es C,la matriz es una técnica de identificar y evaluar interesados Según la descripción eso ya había Sido hecho adecuadamente .Quizás se omitió el registro del interesado apresar der ser evaluado en la matriz.

mesacgonOption: D
Nov 2, 2023

Corrección compañeros en efecto es la D.

58e5964Option: D
Jan 26, 2024

The Stakeholder Engagement assessment matrix has nothing to do with communication or engagement plans related to a stakeholder. The engagement matrix evaluates the level of engagement of a stakeholder, or comparison of engagement of a stakeholder. So if a stakeholder claims they have not been receiving updates, it has nothing to do with the stakeholder engagement matrix.

MsPigeonOption: D
Jul 10, 2024

D. Stakeholder engagement assessment matrix already contains the list of stakeholders (stakeholder register) and determines who shall receive certain communications.