Question 155

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

    Correct Answer: D

    The Stakeholder Engagement Assessment Matrix is the correct document to review. This matrix helps identify gaps between the desired and actual engagement levels of stakeholders. It allows the project manager to evaluate how effectively stakeholders are being engaged and can highlight communication issues, such as a major stakeholder not being informed about recent developments.

Discussion
emelbaOption: D

the stakeholder engagement assessment matrix helps identify gaps between desired and actual engagement levels of stakeholders.

MsPigeonOption: D

D. Stakeholder engagement assessment matrix already contains the list of stakeholders (stakeholder register) and determines who shall receive certain communications.

58e5964Option: D

The Stakeholder Engagement assessment matrix has nothing to do with communication or engagement plans related to a stakeholder. The engagement matrix evaluates the level of engagement of a stakeholder, or comparison of engagement of a stakeholder. So if a stakeholder claims they have not been receiving updates, it has nothing to do with the stakeholder engagement matrix.

mesacgonOption: D

Corrección compañeros en efecto es la D.

mesacgonOption: C

La respuesta es C,la matriz es una técnica de identificar y evaluar interesados Según la descripción eso ya había Sido hecho adecuadamente .Quizás se omitió el registro del interesado apresar der ser evaluado en la matriz.

huynq185Option: C

Check stakeholder register first

Lucky_CindyOption: D

D. Stakeholder engagement assessment matrix

AsakthiOption: D

D. Stakeholder engagement assessment matrix

MuntadherOption: D

After checking Stakeholder register. need to check stakeholder engagement assessment matrix

victory108Option: D

D. Stakeholder engagement assessment matrix

Franco11

is it not consider an issue?

Ade1981

Now the PM is trying to find our the reason for this issue. So he needs to check the engagement document