PMP Exam - Question 1248


During a team meeting the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues. A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Show Answer
Correct Answer: D

When faced with multiple complaints regarding project stability and other critical issues, the new agile project manager should prioritize identifying the root cause to effectively address these concerns. Holding a brainstorming session is an effective way to gather insights from the team, encourage open communication, and collaboratively find the root cause of the problems. This approach is proactive and fosters a team-oriented solution, which is essential in an agile environment.

Discussion

3 comments
Sign in to comment
martinx84Option: D
Jun 20, 2024

Hold brainstorming session to find root cause

omankomanOption: D
Jun 22, 2024

D is the answer.

9RedFox_JBOption: C
Jul 11, 2024

why? why not to document at first and then hold brainstorming session