Exam PgMP All QuestionsBrowse all questions from this exam
Question 111

You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?

    Correct Answer: D

    Identified stakeholders and their information should be recorded in the stakeholder registry. The stakeholder registry is a key document in project and program management that includes a list of stakeholders, their roles, interests, impact, and contact information. This document helps in managing stakeholder engagement and ensuring effective communication throughout the project or program lifecycle.

Discussion
ReevesTOption: D

It is 'Register' not Registry