PMP Exam - Question 843


A project manager is in a team meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do?

Show Answer
Correct Answer: C

When a decision needs to be made regarding a new suggested timeline because of a potential scope change, the project manager should schedule a project decision meeting with all stakeholders to discuss the decision. This approach ensures that all relevant perspectives are considered, promoting transparency, collaboration, and shared ownership of the decision. Through open discussion and analysis, the project manager can gather valuable insights and make an informed decision that aligns with project goals and stakeholder priorities.

Discussion

10 comments
Sign in to comment
SynikalDemon
Sep 5, 2023

A - I almost went with another answer, but yeah is probably right.

Only12goOption: A
Oct 23, 2023

option A, "Follow the stakeholder engagement plan," provides a structured, agreed-upon approach to address such situations. The plan would have guidelines and procedures for how decisions like these should be approached, ensuring consistency and adherence to project governance.

xcjxcjOption: A
Jan 18, 2024

Decision is needed A. Let's see who B. Oldest one decide C. Let us all decide D. I decide A seems correct (relevant people should decide)

AbdelmonmOption: C
Jan 21, 2024

In a situation where a decision needs to be made about a new suggested timeline due to a potential scope change, it's essential to involve relevant stakeholders in the decision-making process. Scheduling a project decision meeting with all stakeholders allows for a collaborative discussion. This approach ensures that different perspectives are considered, and decisions are made collectively. Following the stakeholder engagement plan and involving key stakeholders aligns with best practices in project management.

chlaithemOption: C
Jan 12, 2024

This option emphasizes inclusivity, transparency, and collective responsibility. By scheduling a dedicated meeting with stakeholders: Comprehensive discussion: The project manager can present the situation, potential impacts of the new timeline, and any available alternatives. Stakeholders can voice their concerns, ask questions, and share their perspectives. Informed decision: Through open discussion and analysis, the project manager can gather valuable insights and consider all angles before making a final decision aligned with project goals and stakeholder priorities. Shared ownership: Engaging stakeholders in the decision-making process fosters team unity and acceptance of the chosen path, promoting future collaboration and commitment.

buvana
Mar 20, 2024

C. Schedule a project decision meeting with all stakeholders to discuss the decision.

LNX_RM_AdminOption: C
May 13, 2024

By scheduling a project decision meeting with all stakeholders, the project manager ensures that key decision-makers are involved in the discussion and have the opportunity to provide input and consider the implications of the proposed timeline change. This approach promotes transparency, collaboration, and buy-in from stakeholders, which are essential for effective decision-making and successful project outcomes.

sudersonfernando
Oct 1, 2023

I would go with option C as it promotes transparency in the decision making process by involving stakeholders

David983
Oct 23, 2023

Not ALL the stakeholders need to be involved in the decition like Option C said. It´s more accurate the option A that suggest "Follow the stakeholder engagement plan" in order to involve them on different levels according to each stakeholders characteristics

23169fdOption: A
Oct 7, 2024

The stakeholder engagement plan is designed to outline how decisions are made, who is responsible, and the appropriate level of involvement for each stakeholder. It provides a framework for decision-making that ensures the right stakeholders are involved, based on their roles, influence, and responsibilities in the project. By following the stakeholder engagement plan, the project manager ensures that the decision is made in alignment with the agreed-upon governance and with the appropriate input from relevant stakeholders, ensuring a balanced and informed decision.

AnssooOption: C
Apr 27, 2025

Answer is C.