Exam PgMP All QuestionsBrowse all questions from this exam
Question 213

During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized, the program manager was asked to transition the program into operations.

At this stage, what is expected during the post-review session organized by the program manager?

    Correct Answer: D

    At the stage of transitioning the program into operations, it is crucial to gather feedback and document lessons learned. This helps to understand the effectiveness of the program management and to improve future practices. Therefore, during the post-review session organized by the program manager, the focus should be on collecting feedback and lessons learned from stakeholders and team members.

Discussion
tungdtOption: D

D is correct At this stage of transitioning the program into operations, the focus should be on capturing insights and experiences that can inform future projects and programs. Therefore, during the post-review session organized by the program manager, it is expected to gather: Feedback and lessons learned

happykaurOption: D

At the stage where the program is being transitioned into operations after realizing the intended benefits, during the post-review session organized by the program manager, what is expected is: D. **Feedback and lessons learned** This session would typically focus on gathering feedback from stakeholders and documenting lessons learned. This is an important step for understanding the effectiveness of the program management processes and for improving future programs.