Exam PgMP All QuestionsBrowse all questions from this exam
Question 215

A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by the board of directors.

What should the program manager do before formally closing the program?

    Correct Answer: C

    Before formally closing a program, the program manager should share lessons learned with all program team members. This is crucial for ensuring that knowledge and insights gained during the program are disseminated within the team to improve future projects and programs. By sharing lessons learned, the team can understand what went wrong, what went right, and how to avoid similar issues in the future, contributing to an organization's continuous improvement efforts.

Discussion
tungdtOption: C

C is correct

hanyulinOption: C

C is the right answer