Correct Answer: CThe project manager should assess the impact of the features and refer it to the change control board (CCB). Implementing changes in a project that is 95% complete can have significant consequences on timelines, budget, and resource allocation. A proper impact assessment is necessary to understand these potential impacts, and involving the CCB ensures that all stakeholders have a say in whether the changes should be implemented. This approach aligns with best practices in project management to manage scope changes systematically and with due diligence.