PMP Exam - Question 1210


The sponsor approaches the project manager with new features they want added to the project. The project is 95% complete, but the sponsor insists that continued support for the project relies on the addition of the new features.

What should the project manager do?

Show Answer
Correct Answer: C

The project manager should assess the impact of the features and refer it to the change control board (CCB). Implementing changes in a project that is 95% complete can have significant consequences on timelines, budget, and resource allocation. A proper impact assessment is necessary to understand these potential impacts, and involving the CCB ensures that all stakeholders have a say in whether the changes should be implemented. This approach aligns with best practices in project management to manage scope changes systematically and with due diligence.

Discussion

1 comment
Sign in to comment
martinx84Option: C
Jul 13, 2024

Assess the impact