Question 573

A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach.

What should the project manager do to ensure full compliance of quality requirements during the execution phase?

    Correct Answer: C

    During the implementation phase of a project, the primary focus should be on ensuring that the project deliverables meet the established quality requirements. This is achieved by continually surveying and monitoring the quality of the deliverables. This entails regularly checking the work against quality standards, performing inspections, and implementing quality control measures to identify and rectify any deviations. This ongoing evaluation helps in maintaining high-quality outputs and ensures that the project stays aligned with the specified quality requirements.

Discussion
aishOption: C

Since the project is already in the implementation phase, the Quality Management Plan should have been developed during the planning phase. In this case, the project manager should focus on continually surveying the quality of the deliverables (option C) to ensure that they meet the required quality standards.

SteAleOption: C

https://www.examtopics.com/discussions/pmi/view/55333-exam-pmp-topic-1-question-1738-discussion/

DavidTriOption: C

because of the project is in the implementation phase so the quality requirement is already done and plan quality management is completed before. For now, PM need to continuously monitor quality of deliverable to make sure its qualify

victory108Option: C

C. Continually survey the quality of the deliverable

Dawn6699Option: B

chatGPT: To ensure full compliance of quality requirements during the execution phase of a hydropower plant project managed with a hybrid approach, the project manager should do the following: B. Plan quality management Planning quality management involves identifying quality requirements, standards, and metrics for the project deliverables. It also includes defining quality control and quality assurance processes, resources, and responsibilities for executing the project. The quality plan should specify how processes will be monitored, measured, and reported, as well as how corrective and preventive actions will be taken to address deviations from the quality requirements. The quality plan should be incorporated into the overall project plan and communicated to all stakeholders to ensure alignment and visibility.

cwilson91Option: C

Cannot be B as we're in the implementation phase of the project: "According to PMI best practices, quality management should be planned during the project planning phase and implemented throughout the entire project lifecycle, including the implementation phase."