PMI-SP Exam QuestionsBrowse all questions from this exam

PMI-SP Exam - Question 17


Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that

Fred needs to report to management?

Show Answer
Correct Answer: B

The cost variance for the project is -$51,000. This can be calculated using the formula: Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC). Earned Value is derived by multiplying the Budget at Completion (BAC) by the percentage completion, which is 60%. Thus, EV = 0.60 * $2,456,900 = $1,474,140. Since the Actual Cost to date is $1,525,140, the formula becomes CV = $1,474,140 - $1,525,140 = -$51,000. This indicates that the project is over budget by $51,000.

Discussion

2 comments
Sign in to comment
farbijOption: B
Nov 28, 2019

cost variance =Earned value minus Actual value (not planned value)

Miotti
Jun 5, 2023

Given information: BAC (Budget at Completion) = $2,456,900 Percent Complete = 65% Costs to Date = $1,525,140 Now, let's recalculate the EV: EV = BAC * Percent Complete = $2,456,900 * 65% = $1,596,385 ACWP remains the same: ACWP = Costs to Date = $1,525,140 CV = EV - ACWP = $1,596,385 - $1,525,140 = $71,245 Therefore, the cost variance (CV) for this project, given the updated percentage complete of 65%, is $71,245.

VinKCh
Jul 19, 2024

The project is 60% complete. So, the EV would 0.6*$2,456,900 = $1,474,140. And the CV= EV-AC. Therefore, CV= $1,474,140 - $1,525,140= - $51,000.