Exam PMI-SP All QuestionsBrowse all questions from this exam
Question 17

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that

Fred needs to report to management?

    Correct Answer: B

    The cost variance for the project is -$51,000. This can be calculated using the formula: Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC). Earned Value is derived by multiplying the Budget at Completion (BAC) by the percentage completion, which is 60%. Thus, EV = 0.60 * $2,456,900 = $1,474,140. Since the Actual Cost to date is $1,525,140, the formula becomes CV = $1,474,140 - $1,525,140 = -$51,000. This indicates that the project is over budget by $51,000.

Discussion
Miotti

Given information: BAC (Budget at Completion) = $2,456,900 Percent Complete = 65% Costs to Date = $1,525,140 Now, let's recalculate the EV: EV = BAC * Percent Complete = $2,456,900 * 65% = $1,596,385 ACWP remains the same: ACWP = Costs to Date = $1,525,140 CV = EV - ACWP = $1,596,385 - $1,525,140 = $71,245 Therefore, the cost variance (CV) for this project, given the updated percentage complete of 65%, is $71,245.

VinKCh

The project is 60% complete. So, the EV would 0.6*$2,456,900 = $1,474,140. And the CV= EV-AC. Therefore, CV= $1,474,140 - $1,525,140= - $51,000.

farbijOption: B

cost variance =Earned value minus Actual value (not planned value)