During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.
What approach should be used in this situation?
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.
What approach should be used in this situation?
When a planned activity becomes more complex and needs to be delivered in the shortest time possible, the most effective approach is for the cross-functional team members to work together to complete the activity. A cross-functional team has a diverse set of skills and expertise, enabling them to collaborate and address the complexity of the task efficiently. This approach leverages the strengths of each team member, promotes teamwork, and aligns with agile principles that emphasize adaptability and collaboration. Bringing in external specialists or moving the task to the backlog could introduce delays and disrupt the team's workflow.
D. The cross-functional team members work together to complete the activity. This approach leverages the diverse skills and expertise within a cross-functional team to tackle the complexity of the task. By collaborating closely, team members can identify and implement solutions more efficiently than working in isolation or waiting for external help. This method fosters innovation, accelerates problem-solving, and ensures that different perspectives are considered in addressing the complexity of the activity. It also aligns with agile principles, emphasizing teamwork, collaboration, and the ability to adapt to changing circumstances.
Every one selected D but apparently B look more suitable in this scenario. because If we have already cross-functional team working together and an activity become more complex need to complete quickly. in this case need specialist(subject meter expert). please correct me if I am wrong....
What's happening to exam topics.
The cross-functional team members should work together to complete the activity. This approach promotes collaboration and cross-functional teamwork, which can help identify and address any complexities that arise during the iteration. The team can leverage each other's strengths and knowledge to solve the problem and complete the activity in the shortest time possible. Bringing in an external specialist or moving the work to the backlog may cause delays and disrupt the team's momentum.
O Option D - having the cross-functional team members work together to complete the activity. This approach encourages collaboration, knowledge sharing, and leveraging the diverse skills and expertise of the team to tackle the complex activity effectively. By working together, the team members can brainstorm solutions, support each other, and collectively find the most efficient way to deliver the work in the shortest time possible.
Should be D. It's an Agile common. "Swarming. A technique in which multiple team members focus collectively on resolving a specific impediment."
Answer is D
D sound good. But I think key word: becomes more complex. and delivered in the shortest time possible... -> so need specialíst to help is fastest. Cross-functional team no ensure that having a person expert enough to resolve the complex...
Project team know exactly what is problem and who helpful to help them
Bringing in external support or specialists (options A and B) may introduce delays and go against the principles of a self-organizing team.
Option B is better but can team members decide to bring in specialist. I think it needs to be decided by PM. That is why D is next better choice as cross-functional team member is expected to have more skill to solve the problem. If B is the answer then it should say PM instead of team members.
https://www.examtopics.com/discussions/pmi/view/56747-exam-pmp-topic-1-question-1848-discussion/
Is it the teams responsibility to hire a specialist?
D. The cross-functional team member work together to complete the activity
First try to involve cross functional team members to take their views and if not solved then take help from specialist.
We can go with D, but the real world answer is B.
I will go with B