What project management term would you associated with a predetermined budget you're your program?
What project management term would you associated with a predetermined budget you're your program?
The project management term associated with a predetermined budget for your program is 'cost baseline.' A cost baseline is a time-phased budget that is used as a basis against which to measure, monitor, and control overall cost performance on the project. It represents a project’s expected cost at a given point in time.
C is correct answer. The project management term associated with a predetermined budget for your program is Cost Baseline.