Question 301

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

    Correct Answer: D

    For an ambitious project to gain stakeholder support, it is crucial for the business case to include a feasibility study of the solution. This study helps in assessing whether the proposed solution is practical and achievable within the project’s constraints, such as time, budget, and available resources. A feasibility study would address the stakeholders' concerns about the inefficiency of the work associated with the new project by providing a clear analysis of how the project can be executed successfully.

Discussion
fleeOption: D

D definitely

MizbeeOption: D

The correct answer is D: Feasibility study of the solution