Exam PMP All QuestionsBrowse all questions from this exam
Question 1040

A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project’s required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence.

What should the project manager do?

    Correct Answer: D

    When the identified risk is realized, the project manager must inform the sponsor about the situation. The sponsor and relevant stakeholders need to be aware of the risk realization and its potential impact on the project. After informing the sponsor, a decision can be made on how to proceed, which could involve using the reserve budget, seeking alternative solutions, or making other adjustments to the project plan to ensure its continuation and success.

Discussion
TrytrioOption: D

Its D since the sponsor now needs to make a decision how to continue

Pmpjune152024Option: D

When a risk materializes, it's essential to inform the project sponsor or relevant stakeholders promptly. The project manager should provide all relevant information about the situation, including the impact on the project and potential options for moving forward. Ultimately, the sponsor will need to make a decision on how to address the situation, whether it's finding an alternative solution, allocating additional resources, or adjusting project plans accordingly.

FarnoudamirOption: D

Supplier resource is out of project manager control , so she/he should coordinate with sponsor

mesacgonOption: B

la respuesta es B

UppersquareCapitalOption: D

This option involves transparently communicating with the sponsor about the realized risk and the potential impact on the project. The project manager and sponsor can then discuss available options, such as finding an alternative solution, negotiating with the supplier, or reevaluating project requirements. The decision-making process should involve assessing the implications on the project's objectives, timeline, and budget, and determining the most appropriate course of action to ensure project success.

AbdelmonmOption: D

When a risk is realized, it is essential to communicate this to the project sponsor and relevant stakeholders. In this case, the project manager should inform the sponsor that the software support from the supplier has been discontinued, which triggers the identified risk. The project manager and sponsor can then assess the situation, consider available options, and make informed decisions on how to proceed. This may involve using the reserve budget, seeking alternative solutions, or making adjustments to the project plan.

psvexamOption: B

Ans B Question explicitly states that the vendor is discontinuing support. C is just asking vendor to continue support, while B is explicitly assuring vendor to continue support and that will be paid. So B seems to be more appropriate.

cb4a6c4Option: B

Since reserved budget was planned, advise the supplier that sponsor will pay. Correct answer is B!!

newnewuserOption: C

You have reserve budget for it. Why not use? (These ChatGpt answers are killing me)