Question 852

During project execution, the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are only a few sprints remaining.

What should the project manager do?

    Correct Answer: C

    Working with the team to understand and solve the issues is the most appropriate approach. By collaborating with the team, the project manager can identify the root causes of the lower velocity and high volume of tasks in the testing queue. This approach promotes teamwork, transparency, and continuous improvement, which are key principles in a hybrid project methodology. Simply providing training, adding resources, or increasing sprint duration addresses symptoms rather than the underlying issues and might not lead to sustainable solutions.

Discussion
65f1949Option: C

팀과 협력하여 문제를 이해하고 해결합니다.