During the execution stage. the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.

What should the project manager do first?

    Correct Answer: B

    When a project manager discovers that a team member is unable to complete their work on time and this may impact a milestone, the first step should be to discuss with the team and assess the reasons that led to the delay. Understanding the root cause of the delay is essential before deciding on the next steps. This approach helps in identifying any support needed by the team member, potential process improvements, or adjustments to project timelines without jumping to conclusions or actions that may not address the underlying issue.

Discussion
victory108Option: B

B. Discuss with the team and assess the reasons that led to the delay

Pmpjune152024

Discuss with the team member and assess the reasons that led to the delay