Exam PgMP All QuestionsBrowse all questions from this exam
Question 21

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

    Correct Answer: B

    Integrated Change Control is responsible for evaluating, testing, and documenting changes created to the project scope. It involves the documentation, analysis, and approval or rejection of change requests, ensuring that changes are properly managed and controlled throughout the project lifecycle.

Discussion
[Removed]Option: C

C. Scope Verification Scope verification is the process of formalizing acceptance of the completed project deliverables. It involves reviewing, inspecting, and documenting the project work to ensure that all deliverables have been satisfactorily completed and accepted. When changes are made to the project scope, scope verification becomes crucial in evaluating and documenting these changes to confirm that they meet the specified requirements and have the desired impact on the project.

tungdtOption: C

C is make sense