Exam PMP All QuestionsBrowse all questions from this exam
Question 58

A project manager is working with the team to deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members, causing negative consequences for delivery.

How should the project manager avoid this situation in the future?

    Correct Answer: A

    To avoid future issues with communication channels and ensure timely delivery, the project manager should collaborate with the project team to agree on a suitable communication method and ensure that information is shared consistently. This approach emphasizes the importance of tailoring communication strategies to meet the needs of the team and fosters effective collaboration and information flow.

Discussion
terrypOption: A

Answer A: Involve team and zero down on a suitable collaboration tool.

GanzeeOption: A

A. Agree with the project team on a suitable collaboration and make sure information is shared at all times.

martinx84Option: A

A suitable collaboration

josephsafiranOption: A

Suggested in the the question from the PMO is the key because the role of the PMO is supporting and not leading or controlling, so the PM could negotiate with the team member for the new communication channel

BuviDOption: A

A. Agree with the project team on a suitable collaboration and make sure information is shared at all times.

LhenicaOption: A

Best answer is A

GabMontereyOption: A

A. Collaboration always best for the team

AsakthiOption: B

B- for future use retrsopective is the best solution

TOLANTONGO

To answer B this should be agile but we dont know for sure

MuntadherOption: A

A most fit

victory108Option: A

A. Agree with the project team on a suitable collaboration and make sure information is shared at all times