PMP Exam - Question 587


A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.

What does the project manager need to do first in order to have good project performance?

Show Answer
Correct Answer: C

In order to have good project performance, the project manager needs to first assess the required training per team member. This assessment will identify knowledge gaps and help in planning the necessary training or coaching interventions. It's essential to understand the current level of expertise within the team before deciding on any further steps such as delivering training or changing team members.

Discussion

6 comments
Sign in to comment
randomname123Option: C
Jul 13, 2023

Need to find out what each team member knows first. C is the way to find out who would need answer A.

[Removed]Option: A
Jun 5, 2023

If only some team members do not have the knowledge then it makes sense to train them. Thoughts?

victory108Option: C
Sep 10, 2023

C. Assess the required training per team member

futbool10Option: C
Nov 28, 2023

C. The question is what needs to do first. Assessing comes first before coaching team member. Notice how the answer could pivot to A if the question is "what needs to do" without the "first".

xcjxcjOption: A
Dec 29, 2023

A. Not comfortable with C which all team members are assessed.

DavidTriOption: C
Jul 11, 2024

just having some member lack hybrid knowlege so the first thing PM need to assess to indentify the needed for each member and then make the plan traning and coach them