Question 142

How does a portfolio's collection of work differ from that of a program's collection of work?

    Correct Answer: C

    A portfolio is a collection of projects, programs, and operational activities that are managed together to achieve strategic objectives, but each component may be independent. In a program, the components are typically interdependent and must be managed collectively to achieve specific benefits and outcomes. This independence of components in a portfolio is the key differentiator.

Discussion
tungdtOption: C

C is correct The key difference between a portfolio's collection of work and a program's collection of work is: C. Components may be independent. In a portfolio, the various projects, programs, and operational activities are often managed together to achieve strategic objectives, but they may be independent of each other. In contrast, a program's components are usually interdependent and managed collectively to achieve specific benefits and outcomes.