Exam PMI-RMP All QuestionsBrowse all questions from this exam
Question 44

A heavy industrial design firm has over USS3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.

What is the most effective method to capture these opportunities?

    Correct Answer: D

    To capture identified high-priority opportunities in a project, the most effective method is to establish a contingency reserve. This reserve can be utilized to fund actions that enhance or exploit these opportunities, ensuring that the project benefits from them.

Discussion
ahmedSayisOption: D

D. Establish a contingency reserve.

hossam83Option: D

D is the right answer

TheAWSGuruOption: D

D is the answer

Linkedin_Dario_CondeOption: D

A risk is a Threat or an opportunity, Obviously th identification of this opportunity was done with a PM and to enhance this opportunity we need to establish a contigency reserve so D is correct.

GentleBeatsOption: D

Answer is D Cause it's the actual response to capture the Opportunity. .

OMG4567Option: C

If you the answer would be about a contingency plan to increase the likelyhood of the opportunity it would be C. But the answer is for the reserve and this would not help to capture the opportunity.

joieyaOption: D

Should be option "D"

AllPMIOption: D

In some cases you can use contingency reserve to enhance opportunity or exploit.

RoyalWarriorOption: C

C is correct in assuming this risk assessment was done by a Risk Manager or anyone other than the PM. Once the PM is notified, they will develop a risk response plan along with project stakeholders which may or may not include an contingency reserve.

aws_guru1

There's no indication that the analysis was done without the PM. I think D is the correct answer.