Exam PMP All QuestionsBrowse all questions from this exam
Question 1241

A project manager brings in a new team member from an agile environment to work in a predictive environment. The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

    Correct Answer: C

    To effectively integrate a new team member from an agile environment into a predictive project management environment, it is essential to provide training in the predictive project management approach. This will ensure that the new team member understands the processes, methodologies, and expectations specific to the new environment, enabling smoother collaboration with the existing team and alignment with project goals.

Discussion
c8ee0e6Option: D

As per GPT - Choice A, "Set expectations with the new team member and explain what is needed," is indeed a critical step in integrating a new team member. However, it primarily focuses on one-on-one communication between the project manager and the new team member, rather than fostering team cohesion and transparency. While setting expectations with the new team member (Choice A) is necessary, meeting with all team members to explain the new employee's position (Choice D) is more comprehensive. It not only sets clear expectations but also promotes team cohesion, transparency, and collaboration, which are essential for effective integration and leveraging the new member's agile experience. Therefore, Choice D is the more effective approach in this context.