Lead Implementer Exam QuestionsBrowse all questions from this exam

Lead Implementer Exam - Question 32


What should TradeB do in order to deal with residual risks? Refer to scenario 4.

Show Answer
Correct Answer:

Discussion

1 comment
Sign in to comment
AcrisiusOption: A
Jan 26, 2025

The answer here is A The remaining or residual risk should be documented and subjected to monitoring, review and where appropriate, further treatment. After implementation of a risk treatment plan, there are always residual risks The value of risk reduction following risk treatment should be evaluated, calculated and documented Should be within risk acceptance criteria org must also have residual risk surveillance methods. See day 2 page 125