Exam PCCSE All QuestionsBrowse all questions from this exam
Question 66

A customer has a development environment with 50 connected Defenders. A maintenance window is set for Monday to upgrade 30 stand-alone Defenders in the development environment, but there is no maintenance window available until Sunday to upgrade the remaining 20 stand-alone Defenders.

Which recommended action manages this situation?

    Correct Answer: C

    To manage the situation effectively, the recommended action is to upgrade a subset of the Defenders by clicking the individual Actions > Upgrade button for each Defender that should be upgraded during the respective maintenance windows. This approach allows for upgrading specific Defenders during the available maintenance windows without disrupting the overall environment, especially when there are different maintenance windows for different groups of Defenders.

Discussion
HARRYOption: C

https://docs.paloaltonetworks.com/prisma/prisma-cloud/22-12/prisma-cloud-compute-edition-admin/upgrade/upgrade_defender_single_container

SpippoloOption: C

C. Alternatively, you can select which Defenders to upgrade. Use this method when you have different maintenance windows for different deployments. For example, you might have an open window on Tuesday to upgrade thirty Defenders in your development environment, but no available window until Saturday to upgrade the remaining twenty Defenders in your production environment. In order to give you sufficient time to upgrade your environment, older versions of Defender can coexist with the latest version of Defender and the latest version of Console. https://docs.paloaltonetworks.com/prisma/prisma-cloud/22-12/prisma-cloud-compute-edition-admin/upgrade/upgrade_defender_single_container

Chichi23Option: A

A. Go to Manage > Defender > Manage, then click Defenders, and use the Scheduler to choose which Defenders will be automatically upgraded during the maintenance window.