Question 49

HOTSPOT -

An administrator needs to shut down an AHV cluster to relocate hardware. The administrator upgrades NCC and runs health checks.

Which steps should the administrator perform next?

Item instructions: For each procedure, indicate the order in which that procedure must take place to meet the item requirements.

Hot Area:

    Correct Answer:

    Reference:

    https://next.nutanix.com/how-it-works-22/scheduled-power-outage-relocating-cluster-hardware-if-you-need-to-shut-down-all-the-nodes-in-your-ahv-cluster-here-s- how-37326

Discussion
Tarotest

Step1: Shut down Guest VM Step2: Stop the Cluster Step3: Shut down CVMs Step4: Shut down Nodes https://portal.nutanix.com/page/documents/details?targetId=AHV-Admin-Guide-v5_20:ahv-cluster-shut-down-t.html

adrimcgrady

Shutdown the nodes must be the third step. Every CMV reside in a node. You can't stop it after stop the node.

Cromo19

This is incorrect.