Exam NCM-MCI All QuestionsBrowse all questions from this exam
Question 5

A customer recently set up Async Replication between Site A and Site B. The customer wants to conduct a planned failover and clicks Activate on Site B. The customer then runs the following command on Site A: ncli pd deactivate_and__destroy_vms name=.

What does this do to the customer environment?

    Correct Answer: C

    C

Discussion
pharoah2000Option: D

D is the best answer here 1. power off VMs on Site A, without powering off VM, CLI command won't work 2. run the CLI on Site A > Site A become Secondary 3. power on VMs at Site B

nabilloseOption: C

Correct :C

Cromo19Option: D

With the screenshot from the command output, it is clear that if the VM is not powered off before running it, it fails.

njmadejaOption: D

D. is correct