How many Prism Central instances are required to deploy Leap?
How many Prism Central instances are required to deploy Leap?
To deploy Nutanix Leap, a Prism Central instance is required for each availability zone. This structure allows for effective management and disaster recovery within each zone. Therefore, the requirement is one Prism Central instance per availability zone.
(A) appears to be correct: an instance of Prism Central represents an Availability Zone. However, you don't need PC for Xi Cloud Services AZ. Ref.: https://portal.nutanix.com/page/documents/details?targetId=Leap-Xi-Leap-Admin-Guide-v6_0:ecd-ecdr-introduction-pc-c.html
A is correct.
A looks good : Nutanix Software Requirements Each on-prem AZ (AZ) must have a Leap enabled Prism Central instance. To enable Leap in Prism Central, see Enabling Leap for On-Prem AZ. https://portal.nutanix.com/page/documents/details?targetId=Leap-Xi-Leap-Admin-Guide-v6_1:ecd-ecdr-requirements-pc-r.html