Exam NS0-161 All QuestionsBrowse all questions from this exam
Question 60

Your company has recently decided to stop using the Fibre Channel Protocol (FCP) in the data center. You are asked to decommission FCP and reuse any UTA2 ports to 10 GbE.

Which two steps are involved in this task? (Choose two.)

    Correct Answer: B, C

    To decommission Fibre Channel Protocol (FCP) and reuse UTA2 ports as 10 GbE, you need to destroy any Fibre Channel Logical Interfaces (FC LIFs) hosted on UTA2 ports and remove the FCP license from all nodes in the cluster. Rebooting the nodes is not necessarily required for this task. Removing the FCP license ensures that FCP is completely decommissioned and recycling the UTA2 ports involves eliminating the existing FC configurations, which is achieved by destroying the FC LIFs.

Discussion
loingOptions: BD

A and B

malotru

We are agree ;)