Exam NS0-183 All QuestionsBrowse all questions from this exam
Question 18

Click the Exhibit button.

You are installing a 2-node AFF A400 switchless cluster. You have cabled the management network to the e0M port. NetApp also recommends cabling to a redundant management network switch.

Referring to the exhibit, to which port should the redundant management network be cabled?

    Correct Answer: C

    To set up a redundant management network for a 2-node AFF A400 switchless cluster, you should cable the redundant management network to the e0P port. In the exhibit, port 1 (e0P) is clearly labeled for management purposes.

Discussion
Guss_122Option: D

4 is the good answer. e0b is normally used for Interconnect