MB-320 Exam - Question 81


HOTSPOT -

You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.

You need to schedule the order.

Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Exam MB-320 Question 81
Show Answer
Correct Answer:
Exam MB-320 Question 81

References:

https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/operation-scheduling-options

Discussion

1 comment
Sign in to comment
viking1
Jul 26, 2021

Correct, use operations scheduling for scheduling at resource group level, and schedule backward from delivery date as specified in the question.