MB-320 Exam - Question 65


DRAG DROP -

A company that uses Lean manufacturing concepts to produce paper plates has redesigned the layout of the warehouse and production floor.

The company's production flow activities no longer match the tasks of the workers. Employees use paper and manual communication to complete the tasks.

You need to update the production flows to match their current processes by deactivating the obsolete production flows and creating new ones.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
ZVV
Feb 16, 2021

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/deactivate-production-flow-version To expire an active production flow version, you need to set an expiry date. In that sense, deactivation is more like an exception than a rule. But there is no such options in the question...

ZVV
Feb 22, 2021

Define product quantities and kanban quantities and Configure events are the parts or Create Kanban rule process, so the question is really poor...

Alexpet
Nov 1, 2021

Creating Kanban rules covers everything so is more complete. The provide answer looks correct.https://www.examtopics.com/exams/microsoft/mb-320/view/17/#

Alexpet
Nov 1, 2021

Creating Kanban rules covers everything so is more complete. The provide answer looks correct.https://www.examtopics.com/exams/microsoft/mb-320/view/17/#

ElAndo
Apr 9, 2021

I think the correct order is 3, 2, 6, 4, 5

Daichisan
Oct 26, 2021

4,1,8,3,2 should be correct