MB-320 Exam QuestionsBrowse all questions from this exam

MB-320 Exam - Question 73


Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.

You need to create a subcontracting activity for the painting service.

Solution:

1.) Create a vendor warehouse for the subcontracting vendor

2.) Create a vendor resource and add it to a new work cell for outsource painting

3.) Create a production flow transfer activity and specify the vendor warehouse as the target warehouse

Does this solution meet the goal?

Show Answer
Correct Answer: B

The solution involves creating a vendor warehouse, a vendor resource, and specifying the vendor warehouse in a production flow transfer activity. However, the painting operation described is a process activity, not a transfer activity. Therefore, the provided steps do not appropriately address the need for creating a subcontracting activity for a process-based service like painting. The correct answer is 'No'.

Discussion

2 comments
Sign in to comment
ArieV
Jul 7, 2021

My answer is A https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/activity-based-subcontracting#subcontracted-transfer-activities Recipient – The activity is subcontracted if the transfer to the warehouse is managed by a vendor (as defined by a property of the warehouse). All selected purchase agreements for services must have the same vendor ID as the warehouse.

Alexpet
Nov 1, 2021

Because this is an outsource painting activity, you cannot use this option. These options are reserved for transfer activities, but the painting is a process activity. The correct answer is B.

Daichisan
Oct 26, 2021

A should be correct