Question 90

A company has three jobs in a job queue. JobB and JobC start while JobA is in progress. The following table shows the estimated production time for each job.

The actual work hours and total bundle time are shown in the following table.

You need to calculate the allocated time for JobA by using a Job allocation key.

What is the total allocated time for JobA?

    Correct Answer: A

    The total allocated time for JobA is 1 hour. This is because JobA has an estimated production time of 1 hour according to the given table. The production time for JobA does not change regardless of the total bundle time or any allocation keys, as it directly corresponds to the production time specified.

Discussion
AngielineOption: B

This is correct. https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/about-allocation-keys Bundle time 6 / 3 jobs = 2hrs