Question 55

HOTSPOT -

A candy manufacturer uses Dynamics 365 Supply Chain Management.

A master planning run needs to prioritize the production jobs for fruit snacks by flavor and color every 16 days.

You need to configure the appropriate parameters in the coverage group.

What should you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

    Correct Answer:

Discussion
dkh2207

The key here is Priority, it should be Sequencing.

MFool

Agree, it should be Sequencing and Days

CPSKCtestaccount

https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/set-up-sequencing-parameters-for-a-master-plan