MB-320 Exam QuestionsBrowse all questions from this exam

MB-320 Exam - Question 135


DRAG DROP -

You need to set up the system to calculate the overhead rates automatically for production.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Show Answer
Correct Answer:

Set up and configure manufacturing

Discussion

3 comments
Sign in to comment
ZVV
Feb 23, 2021

You can't assign cost group directly to resources - you need to assign it to cost category instead. https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/cost-groups https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/cost-categories-used-production-routings

Alexpet
Oct 31, 2021

In that case it should be: 1. Create cost groups. 2. Create price total and cost group nodes on costing sheet. 3. Create overhead calculation node to materials as surcharge and labor as rate for setup time. 4. Define the basis for calculating cost as absorption.

Daichisan
Oct 26, 2021

4,5,7,2 should be correct

ElAndo
Apr 11, 2021

I think the answer is: 4. Create cost groups 7. Create price total and cost group nodes on costing sheet 2. Create overhead calculation node for materials as surcharge and labor as rate for setup time 5. Associate cost groups to items and cost categories