Exam MB-335 All QuestionsBrowse all questions from this exam
Question 65

A company is implementing Dynamics 365 Supply Chain Management in their manufacturing environment. The manufacturing process uses formulas to direct material consumption on the batch orders.

During production some items in the formula must be consumed automatically from the production area, while some must be picked with their actual consumption reported on a pick list.

You need to determine which setup method is used for formula lines to allow for the desired mixed method picking processes.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution,

NOTE: Each correct selection is worth one point.

    Correct Answer: A, B

    The goal is to achieve mixed method picking processes in a manufacturing environment using Dynamics 365 Supply Chain Management. Setting the flushing principle on each formula line based on the consumption method for the line ensures that some items are automatically consumed while others can be picked manually, making it a suitable method. Additionally, leaving the flushing principle blank on formula lines and setting a default flushing principle on the items based on the consumption method for the item enables a default handling mechanism for items whose specific line handling is not set, allowing for mixed consumption methods for the items during production.

Discussion
MamaouOptions: AB

For me it's A and B, A it's the base of the flushing principle functionality. and and it's blank a the formula level, the system takes form the item. C can't be an answer for me because the resource consumption is used to determine where the raw materials it takes not how.

MFoolOptions: AB

I will go with A and B.

GiSi1965Options: AB

The default flushing principle on the production BOM lines or batch order formula lines is taken from the product or the overridden value on the BOM or formulas.

TonheidieOptions: BC

The hierarchy starts at the released product, where the flushing principle has the value Start. On the bill of materials (BOM) or formula line, the flushing principle from the product can be overridden. The default flushing principle on the production BOM lines or batch order formula lines is taken from the product or the overridden value on the BOM or formulas. (So the answer A takes 'more time', therefor I think this B over A) https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/flushing-principles

LucasK69Options: AD

Its A/D, The default flushing principle on the production BOM lines.

LOR_19Options: AC

A and C is correct. They asked for metod used for formula lines.