MB-320 Exam - Question 105


You are the lead product design engineer at a plastics manufacturing company. You implement a new process that uses a single tool to produce three finished goods at the same time.

You need to set up the planning item number and formula to correctly to manufacture the three items.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Show Answer
Correct Answer: ADE

In setting up the planning item number and formula for manufacturing three items at the same time, you need to perform the following actions: Create item number for planning item and the associated formula to define what will be produced and the relationship between materials. Assign co-products to the formula, as the formula must detail which items are considered as co-products in the manufacturing process. Specify each of the finished good items as co-products to ensure that all items produced are accounted for within the formula.

Discussion

2 comments
Sign in to comment
viking1
Jul 27, 2021

ADE is correct. First, create (or release) the product that is to be the planning item and then, in the "Engineer" fast tab, field group "FORMULA PLANNING", select "Planning item" in "Production type". Next, create the formula. On the formula versions form, click "Co-products" in the action pane, "Formula version" tab. Add lines for the co-products. Note that only released products with a production type of "Co-product" or "By-product" will be shown in the drop-down.

ZVV
Feb 18, 2021

https://docs.microsoft.com/en-us/learn/modules/configure-use-process-manufacturing-dyn365-supply-chain-mgmt/19-planning-items