MB-320 Exam - Question 11


DRAG DROP -

A manufacturer uses route operations and job scheduling.

You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.

You need to adjust the efficiency percentage for the conveyor line calendar.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Exam MB-320 Question 11
Show Answer
Correct Answer:
Exam MB-320 Question 11

Discussion

5 comments
Sign in to comment
ThomasVanDorpe
Jun 5, 2020

In the question is said that it is a unique calendar for the conveyer belt. I would choose the sequence: Select calendar related to resource - Working times - Update efficiency for the days that need the change

sadiq_d365
Feb 8, 2021

316 correct sequence

KesJ
Oct 11, 2020

Agree with you Thomas. I wonder how is it possible to "Attach the new template to the calendar"?

Pir
Jun 4, 2021

3, 1 and 6 are correct since calendar is unique and we want temporary change in existing calendar.

viking1
Jul 26, 2021

3, 1 and 6. Select the calendar related to the resource and then, from the "Working times" form, update the efficiency for the affected days.