AZ-400 Exam - Question 294


You have a project in Azure DevOps named App Project that is used to develop an app named App1. App1Project has an Azure Boards team dashboard that is used to monitor the progress of App1 and track work items.

You need to track how long it takes to close a work item once work for the item has commenced.

Which type of widget should you add to the dashboard?

Show Answer
Correct Answer: D

To track how long it takes to close a work item once work commences, the appropriate type of widget to add to the dashboard is 'cycle time'. Cycle time measures the duration it takes to complete a work item from the moment work begins to when it is closed. This metric specifically tracks the time from commencement of work to completion, making it the most suitable option for the given requirement.

Discussion

9 comments
Sign in to comment
TechyNettyOption: D
Jan 18, 2024

It should be Cycle Time (key word commenced/started)

mjansenOption: D
Apr 15, 2025

Commenced... nice Microsoft.

ZippomasterOption: D
Jan 17, 2024

https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cumulative-flow-cycle-lead-time-guidance?view=azure-devops

xdaOption: D
Jan 21, 2024

Has to be "D"

MunwalinwaliOption: D
Jan 26, 2024

The answer is D, "commenced" not created.

xdaOption: D
Jan 30, 2024

D: commenced is started > Cycle Time

FeriAZOption: D
Mar 13, 2024

Cycle time measures the average time it takes to complete a work item, from the moment it's activated (when work begins) to when it's closed (considered finished). This aligns perfectly with your need to track how long it takes to close work items after work commences.

MatttOption: D
May 24, 2024

Should be D

marmilaOption: D
Aug 21, 2024

Commenced means started, the correct answer is D