A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.

You need to create a subcontracting activity for the painting service.

Solution:

1.) Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01

2.) Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell

3.) Create a production flow process activity using the painting work cell and the service item as the picking activity

4.) Create a service term on the activity to tie the purchase agreement to the activity

Does this solution meet the goal?

Show Answer
Correct Answer: A

The solution describes the correct steps necessary to create a subcontracting activity for a painting service in a manufacturing plant using Lean processes. This involves creating a purchase agreement with the subcontracting vendor that includes pricing information, setting up a vendor resource and work cell for the outsourced painting, using the painting work cell and service item in the production flow process activity, and tying the purchase agreement to the activity through a service term. These steps are aligned with proper procedures for handling outsourced services.