Question 63

DRAG DROP -

A manufacturing company is implementing Dynamics 365 Supply Chain Management.

You have a bill of materials (BOM) for each finished good. Finished goods may have subcontracted operation steps.

You need to configure the BOM lines.

What should you configure? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

    Correct Answer:

Discussion
Angieline

Correct https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/about-line-types

MFool

Should not be Pegged supply - to explote sub-boms and Vendor line (correct)

MFool

Never mind, correct. Phantom and vendor.