You are the lead product design engineer at a plastics manufacturing company.

You implement a new process that uses a single tool to produce three finished goods at the same time.

You need to set up the planning item number and formula to correctly to manufacture the three items.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

    Correct Answer: A, B, D

    To set up the planning item number and formula for manufacturing three items simultaneously, you need to create an item number for the planning item and its associated formula to track and manage production. Specify each finished good item as a co-product since they are produced together. Assign these co-products to the formula to ensure they are correctly accounted for in the production process.